Craig's RV-14A Build
Home
(6951 Total Hrs)
Avionics
(22 Hrs)
Fwf
(43 Hrs)
Inventory
(4.5 Hrs)
Other
(19.5 Hrs)
Section 14
(10.5 Hrs)
Section 18
(30.5 Hrs)
Section 19
(37.5 Hrs)
Section 20
(3 Hrs)
Section 36
(2 Hrs)
Section 38
(55.25 Hrs)
Section 39
(51 Hrs)
Section 40
(43.5 Hrs)
Section 42
(6.5 Hrs)
Section 43
(52 Hrs)
Section 44
(6.5 Hrs)
Section 45
(71.5 Hrs)
Section 46
(26 Hrs)
Section 47
(15 Hrs)
Section 48
(7.5 Hrs)
Section 49
(15.5 Hrs)
Section 50
(10.5 Hrs)
Section 51
(1.5 Hrs)
Section 54
(4 Hrs)
Section 59
(1 Hrs)
Section 60
(4 Hrs)
Section 62
(15.5 Hrs)
Section 9
(13 Hrs)
Wings
(7 Hrs)
Fabricate cowl hinges and pins.
19 Apr 2024
3 hours
Section 45
#April-2024
#wes-April-2024
Share
Assembled and painted interior parts. Installed seat belts
15 Apr 2024
3.5 hours
Section 42
#April-2024
#bryan-April-2024
Share
Installed connector for wires to canopy. Installed engine.
5 Apr 2024
4 hours
FWF
#April-2024
#wes-April-2024
Share
Cowl flap
1 Apr 2024
5 hours
Section 62
#April-2024
#bryan-April-2024
Share
Finished inventorying. Primed parts. Started riveting interior parts
29 Mar 2024
3 hours
Section 42
#March-2024
#bryan-March-2024
Share
Remove previously installed control cable bracket. Drill and prep new bracket. Install all control cables into new bracket.
29 Mar 2024
5 hours
Section 50
#March-2024
#wes-March-2024
Share
Install prop and alt air cables. Install heater cables and check operation. Help with inventory.
25 Mar 2024
5.5 hours
Section 50
#March-2024
#wes-March-2024
Share
Inventory
25 Mar 2024
4.5 hours
Inventory
#March-2024
#bryan-March-2024
Share
Deburred, scuffed and cleaned parts
22 Mar 2024
4 hours
Section 62
#March-2024
#bryan-March-2024
Share
Installed connections on back of engine in preparation for engine installation. Vinyl wrapped control bracket.
22 Mar 2024
5 hours
Section 43
#March-2024
#wes-March-2024
Share