Craig's RV-14A Build
Home
(579.25 Total Hrs)
Avionics
(22 Hrs)
Fwf
(43 Hrs)
Inventory
(4.5 Hrs)
Other
(19.5 Hrs)
Section 14
(10.5 Hrs)
Section 18
(30.5 Hrs)
Section 19
(37.5 Hrs)
Section 20
(3 Hrs)
Section 36
(2 Hrs)
Section 38
(55.25 Hrs)
Section 39
(51 Hrs)
Section 40
(43.5 Hrs)
Section 42
(6.5 Hrs)
Section 43
(52 Hrs)
Section 44
(6.5 Hrs)
Section 45
(71.5 Hrs)
Section 46
(26 Hrs)
Section 47
(15 Hrs)
Section 48
(7.5 Hrs)
Section 49
(15.5 Hrs)
Section 50
(10.5 Hrs)
Section 51
(1.5 Hrs)
Section 54
(4 Hrs)
Section 59
(1 Hrs)
Section 60
(4 Hrs)
Section 62
(15.5 Hrs)
Section 9
(13 Hrs)
Wings
(7 Hrs)
Finished oil door and installed.
29 Jul 2024
2 hours
Section 45
#July-2024
#wes-July-2024
Share
Finished upper and lower intersection fairings
29 Jul 2024
4.5 hours
Section 43
#July-2024
#bryan-July-2024
Share
Worked on oil door
27 Jul 2024
2 hours
Section 45
#July-2024
#wes-July-2024
Share
Finished sanding top cowl air dams. Began installation of oil door
22 Jul 2024
5 hours
Section 45
#July-2024
#wes-July-2024
Share
Drill holes in bottom cowl and test fit to fuselage. Sand and bondo air dams (ready for sanding). Prepare oil door for installation.
19 Jul 2024
2.5 hours
Section 45
#July-2024
#wes-July-2024
Share
Started work on intersection fairings
19 Jul 2024
3.5 hours
Section 43
#July-2024
#bryan-July-2024
Share
Install left and right air dams using epoxy/flox mixture.
15 Jul 2024
2.5 hours
Section 45
#July-2024
#wes-July-2024
Share
Trimmed and positioned left and right inlet ramps on to top cowl..
12 Jul 2024
3 hours
Section 45
#July-2024
#wes-July-2024
Share
Install all hinges on lower and upper cowling.
9 Jul 2024
3 hours
Section 45
#July-2024
#wes-July-2024
Share
Drill and cleco upper cowl hinge. Drill and rivet nut plates to lower cowl. Debur all hinges.
8 Jul 2024
4 hours
Section 45