Craig's RV-14A Build
Home
(579.25 Total Hrs)
Avionics
(22 Hrs)
Fwf
(43 Hrs)
Inventory
(4.5 Hrs)
Other
(19.5 Hrs)
Section 14
(10.5 Hrs)
Section 18
(30.5 Hrs)
Section 19
(37.5 Hrs)
Section 20
(3 Hrs)
Section 36
(2 Hrs)
Section 38
(55.25 Hrs)
Section 39
(51 Hrs)
Section 40
(43.5 Hrs)
Section 42
(6.5 Hrs)
Section 43
(52 Hrs)
Section 44
(6.5 Hrs)
Section 45
(71.5 Hrs)
Section 46
(26 Hrs)
Section 47
(15 Hrs)
Section 48
(7.5 Hrs)
Section 49
(15.5 Hrs)
Section 50
(10.5 Hrs)
Section 51
(1.5 Hrs)
Section 54
(4 Hrs)
Section 59
(1 Hrs)
Section 60
(4 Hrs)
Section 62
(15.5 Hrs)
Section 9
(13 Hrs)
Wings
(7 Hrs)
Finished inventorying. Primed parts. Started riveting interior parts
29 Mar 2024
3 hours
Section 42
#March-2024
#bryan-March-2024
Share
Inventory
25 Mar 2024
4.5 hours
Inventory
#March-2024
#bryan-March-2024
Share
Deburred, scuffed and cleaned parts
22 Mar 2024
4 hours
Section 62
#March-2024
#bryan-March-2024
Share
Installed canopy seals and pins. Started prepping interior parts
18 Mar 2024
4.5 hours
Section 39
#March-2024
#bryan-March-2024
Share
Final sand and prime layup. Installed seals. Prepped for other seals.
12 Mar 2024
3 hours
Section 39
#March-2024
#bryan-March-2024
Share
Applied body filler and sanded layup. Installed rear seal. Cut seals. Prepped surfaces for seal installation.
11 Mar 2024
4.5 hours
Section 39
#March-2024
#bryan-March-2024
Share
Sanded canopy
8 Mar 2024
4 hours
Section 39
#March-2024
#bryan-March-2024
Share
Canopy fiberglass lay up
4 Mar 2024
4.5 hours
Section 39
#March-2024
#bryan-March-2024
Share
� 2023